Lume Power is a two-phase natural gas generating facility planned near Franklin, Georgia.
Scroll · Enter the project- 01 Site
- 02 Permit
- 03 Build
- 04 Operate
A 330-acre site on Sellers Road near Franklin.
The property is about 40 miles southwest of Atlanta, next to the Georgia Transmission Corporation 230 kV system and within 3 to 5 miles of the Transco pipeline. Project 1 occupies 13 acres and Project 2 occupies 11.2 acres.
Permitting is underway with state, federal, and local agencies.
Environmental field surveys are complete and the air permit application was submitted to Georgia EPD on September 29, 2026. The land use and special use permit is in review with Heard County, and construction permits are expected in summer 2027.
Two phases of construction on a single site.
About 210 construction workers at peak per phase sourced from Heard County and the Atlanta metropolitan area. Project 1 is built first, followed by Project 2.
836 MW of fast-start capacity for the regional grid.
Project 1 adds 458 MW from late 2028, and Project 2 adds 378 MW in 2029, using industrial gas turbines of about 38 MW each in simple cycle. The facility supports at least 21 permanent positions over an operating life of 30 years or more.
What the project means for Heard County.
Two phases of natural gas generation totaling 836 MW, bringing construction jobs, permanent operations positions, and reliable fast-start power to Heard County.


Site location and infrastructure.
Lume Energy Center will serve the local electricity market and provide grid reliability for Georgia. This project site was chosen due to its proximity to existing power-related critical infrastructure.


- Project 1 13 acres
- Project 2 11.2 acres
Regulatory review and permitting.
Construction permits for Projects 1 and 2 are expected within 12 months across federal, state, and local review.
Environmental field surveys
Army Corps · FWS · SHPOBiological, cultural, and waters of the U.S. delineations completed on the property.
CompletePre-application meetings
Georgia EPD · Heard CountyAir permit pre-application meeting with Georgia EPD on August 12, 2026, and a planning and zoning pre-application meeting.
CompleteAir permit application
Georgia EPDSynthetic minor source application with Title V operating permit submitted September 29, 2026.
SubmittedLand use and special use permit
Planning and Zoning · CommissionersRezoning from agricultural to industrial with a special use permit, followed by public review.
In progressConstruction permits issued
Heard County · Fire MarshalBuilding, grading, fire, sanitary, and related local permits, pending final engineering.
Expected
Meetings and announcements.
Upcoming public meetings are listed here as they are scheduled. Dates, locations, and materials will be added as they are confirmed.
Heard County Planning Board
201 Park Ave, Franklin, GA
Heard County Board of Commissioners
201 Park Ave, Franklin, GA
Project inquiries.
Questions about the project? Send an inquiry using the form, or email info@kindle-energy.com. Project updates, public meeting dates, and supporting documents will be published here as they become available.